Flexsol manufactured a warehouse for UAN. Tanks were installed in Burin, Sumy region, and Kremenets, Ternopil region.
Excluding site preparation, installation at each location took two days. This is one of the many advantages of installing Flexsol flexible tanks: it does not require construction work, foundation construction, or permits.
Installation of soft storage tanks for UAN with a total volume of 4000 m³ was completed.
In the city of Burin, two pools were installed with tanks of two 500 m³, 325 m³ and two 385 m³ tanks.
For the location in Kremenets, four 500 m³ tanks were installed in a protective basin.